Проєкти

Pneumatic conveying of bulk materials


An example is the situation at a recently launched Russian plant for processing dolomite rock.

At the first start-up of the equipment, the problem of pneumatic transportation of dolomite flour with a fraction of up to 3 mm was revealed. at a distance of 140 m.

Initially, a Turkish-made jet chamber pump with a volume of 1m3 was installed at the production site, during which dolomite flour hopelessly lay in the pipeline, thereby causing a stop the entire line. Subsequently, the pump manufacturer proposed to replace the existing pump with the same but larger volume – 3m3. In the end, the result was the same.

After receiving a request to solve this problem, our specialists developed and subsequently successfully implemented a project for transporting dolomite flour based on “Beaver-technology”.< /p>

Turkish installation was replaced by a pneumatic chamber pump “Biver 5000B” with a volume of 5m3. The existing conveying pipeline was also completely redesigned and replaced, using the method of lower insertion into the cone of the receiving silo and installing an active flow stabilization unit. As a result, it was possible to achieve stable operation and productivity up to 60 t/h, reduce the cost of compressed air and increase the service life of the equipment.

The situation is described in more detail in one of the articles on our sitete.


 

Supply of calcide, gypsum and titanium oxide powder to supply hoppers based on "Beaver technology"

Powder Pneumatic Conveying System

Pneumatic conveying system for feeding calcide, gypsum and titanium oxide powder into supply hoppers based on “Beaver technology”.
The production belongs to one of the leading manufacturers of paint and varnish products in the Russian Federation.

The system of pneumatic supply of powdered material to the feed hoppers of dissolvers performs the following functions:

  • Big bag unpacking with pneumatic loading of incoming material into storage silos
  • Material feed to dissolver feed hoppers
  • Metering the material feed according to the given recipe
  • Return of transported air with dusty suspension of transported material
    into the original silo for aspiration, avoiding mixing of different types of materials
Pneumatic conveying line for fresh sand and reclaimed sand with "Beaver 1500" or "Beaver 5000" pump

Pneumatic Sand Conveying

The line provides pneumatic transport of sand
and regenerate through the pipeline at a distance of up to 120m
at a speed of 2 m/s, with the declared capacity
12-15 incl.

The system for supplying fuel pellets (pellets) to the silo by pneumatic transport, at one of the private boiler houses

Pneumatic lifting line for fine materials up to 500 m

Pneumatic hoist of fine materials to a height of up to 500 meters with a capacity of 90-180 t/h

Elevator specifications:

  • Number of elevator pneumatic transport units BEPT, pcs — 40
  • Number of PTEK elevator columns, pcs — 40
  • Elevator string diameter, mm — 620/720
  • Diameter of the conveying pipe, mm — 275/325
  • The volume of the elevator column is working, m3 – 2.7 / 3.6
  • The volume of the elevator column is geometric, m3 — 3.5/4.6
  • Weight of loaded product, t — 3.0/4.0
  • Working pressure, MPa — 0.2/0.3
  • Design pressure, MPa — 0.40
  • Test pressure, MPa — 0.45
  • Safety valve setting pressure, MPa — 0.50
  • Number of air purification filters, pcs — 10
  • Resistance of filters before regeneration, MPa — 0.010
  • Filting surface area, m2 — 7.0/10.0

Halite dust is loaded into the pneumatic elevator through the PKNB-3/5N pneumatic chamber pump through a DN150/200mm pipe in portions of 3-4 tons with a capacity of 90/130/180 t/h.

The air displaced from the chamber of the pneumatic transport elevator column is discharged into the air discharge line DN200/250mm, mounted along the pneumatic elevator.
Halite dust is loaded into the pneumatic chamber pump through a receiving hopper with a capacity of 3-5 m3.

Big-bag container unpacking station

Unpacking “Big-Bag” containers with further pneumatic conveying of the material.

Characteristics of the station equipped with the “Beaver 1500” pump

Installation performance up to 18 incl. Pitch distance 150 m. Feed Height 20 m. Compressed air consumption Р=0.3MPa – 3.5m3/t Energy costs 0.4 kWh/t
Port Bulk Terminal of Mineral Fertilizers

Pneumatic conveying of mineral fertilizers

Pneumatic conveying line for mineral fertilizers with loading into ships, with a capacity of up to 250t.h.
The line is based on two pneumatic chamber pumps “Biver 10” operating in antiphase for continuous supply of material in a dense layer at a speed of 2-3 m/s.


Залишіть заявку та дізнайтесь точну вартість обладнання:

Запит техніко-комерційної пропозиції